PROJECTS  FUNDED BY THE MINISTRY OF DONER, GOVERNMENT OF INDIA

 

i) Water supply scheme for 24 villages of Chiephobozou R.D. Block (NLCPR):

 

With an approved cost of Rs. 2626.41 lakh, the project is intended to provide drinking water supply to one of the most water scarce Blocks in Nagaland. Physical progress as in February 2018 is 98% and completion has been re-scheduled to 2018-19.

 

 

 

ii) Augmentation of water supply to Wokha Town (NLCPR):

 

With an approved cost of Rs. 1959.60 Lakh the project is designed for a capacity of 3.75 mld.  Major works in the project include diversion weirs, RCC circular desilting, sedimentation tank, rapid sand filter, pumping units and water distribution system. 98 % of the works are complete and is scheduled for completion during 2018-19.

 

 

 

iii) Providing water supply to New Peren District Headquarter (NLCPR):

 

This project with an approved cost of Rs. 930.94 lakh is under implementation to provide drinking water supply to the newly established Peren District headquarter. Laying, fitting and fixing of 80 mm dia. main pipeline has been completed while that of 100 mm dia. pipeline and other civil works such as construction of water treatment plant and service reservoirs are in progress, with 93% completion. Fitting of 100 mm dia main pipeline and treatment unit for New Peren water supply project. The project is targeted for completion during the year 2018-19

 

 

 

iv) Providing Water Supply to Mon village and four surrounding villages- Lempong Sheangha, Phuktong, Tuimai and Leangnyu in Mon district:

 

This project has been approved for an estimated cost of Rs. 1546.67 lakhs by the Ministry of DoNER in 2015-16 and 79 % of works have been completed. The project is targeted for completion during the year 2018-19.

 

 

 

v) Providing Water Supply to Samzuiram Village at Peren District(NLCPR):

 

The Project was sanctioned during the year 2017-18 with an estimated cost of Rs. 1893.16 lakh. The project is yet to start.

 

 

 

vi) Providing Water Supply by gravity to Aboi HQ and Longching EAC HQ at Mon District.

 

The Project was sanctioned during the year 2017-18 with an estimated cost of Rs. 965.98 lakh. The project is yet to start.

 

 

 

vii) Augmentation of water supply scheme through stream water sources in Japukong Range, Mokokchung district (NEC):

 

This is one of the two water supply projects ever sanctioned by the Ministry of DoNER under NEC in PHED, Nagaland. The project covers 5 (five) villages of Japukong Range. The project was sanctioned at an estimated cost of Rs. 484.74 lakh during 2013-14. Physical progress is 67%.

 

 

 

viii) Providing water supply to Akuk old Village by pumping in Wokha district (NEC):

 

The project is sanctioned at an estimated cost of Rs. 285.22 lakhs and 85% of works have been completed . This project is targeted to be completed by 2018-19.

 