PROJECTS FUNDED BY OTHER MINISTRIES / AGENCIES
i) Providing Water Supply to Mon village and four surrounding villages - Lempong Sheangha, Phuktong, Tuimai and Leangnyu in Mon district (under NLCPR):
This project was sanctioned during 2015-16 for an estimated cost of ₹ 1546.67 lakh by the Ministry of DONER. The physical pogress is 85% and is targeted for completion during the year 2020-21.
ii) Providing Water Supply to Samzuiram Village at Peren District (NLCPR):
This project was sanctioned during the year 2017-18 for an estimated cost of ₹ 1893.16 lakh. The project is under execution and anticipated expenditure upto January 2021 is ₹ 870.85 lakh with a physical progress of 78%.
iii) Providing Water Supply by gravity to Aboi HQ and Longching EAC HQ at Mon District (under NLCPR).
This project was sanctioned during the year 2017-18 for an estimated cost of ₹ 965.98 lakh. The project is under execution and anticipated expenditure upto January 2021 is ₹ 444.35 lakh during 2020-21 with a physical progress of 72%.
iv) Augmentation of water supply scheme through stream water sources in Japukong Range, covering 5(five) villages under Mokokchung district (NEC):
This project was sanctioned during the year 2013-14 for an estimated cost of ₹ 484.74 lakh. Financial progress is 100% and is targeted for commission by March 2021.