i) Providing Water Supply to Mon village and four surrounding villages- Lempong Sheangha, Phuktong, Tuimai and Leangnyu in Mon district (under NLCPR):

This project was sanctioned during 2015-16 for an estimated cost of ₹ 1546.67 lakh by the Ministry of DoNER . The physical progress is 85 % and is targeted for completion during the year 2020-21.

ii) Providing Water Supply to Samzuiram Village at Peren District (NLCPR):

The Project was sanctioned during the year 2017-18 for an estimated cost of ₹ 1893.16 lakh. The project is under execution and anticipated expenditure upto January 2021 is ₹ 870.85 lakh with a physical progress of 78%.

 

iii) Providing Water Supply by gravity to Aboi HQ and Longching EAC HQ at Mon District (under NLCPR).

The Project was sanctioned during the year 2017-18 for an estimated cost of        ₹ 965.98 lakh. The project is under execution and anticipated expenditure upto January 2021 is ₹ 444.35 lakh during 2020-21 with a physical progress of 72%.

 

iv) Augmentation of water supply scheme through stream water sources in Japukong Range, covering 5(five) villages under Mokokchung district (NEC):

The project was sanctioned  during the year 2013-14 for an estimated cost of ₹ 484.74 lakh. Financial progress is 100% and is targeted for commission by March 2021.